ITEM DETAILS
CEC #3972
Year2013
Date Received2013-08-20
ApplicantWater and Sewerage Authority (WASA)
Project DescriptionInstallation of 5 km of a 300 mm transmission pipeline, 1.1 km of 150 mm distribution pipeline and its appurtenances including interconnection on side streets, transfer of services, new service connections, bridge and culvert crossings and road reinstatem
Designated Activity40(b)
LocationFrom Todds Road Booster Station along Caparo brasso Valley main Road to Mamoral road
StatusIssued CEC
Status Date2013-09-27