| ITEM | DETAILS |
|---|---|
| CEC # | 1296 |
| Year | 2005 |
| Date Received | 2005-12-29 |
| Applicant | Essar Steel Caribbean Limited |
| Project Description | clearing, grading, cutting and back filling of 203ha of land. The construction of Integrated Steel Complex consisting of 4.5 MTPY Pellet Plant, 2x1.5 MTPY HBI, 2.7 MMTPY HRC- electricity arc furnace, slab caster, hot strip mill, 160 MW+ 160 MW CPP, 360 m3 |
| Designated Activity | N/A |
| Location | Point Lisas |
| Status | No CEC required |
| Status Date | 2006-03-09 |